How to write a monthly facilities management report

A monthly facilities management report tells the people responsible for a site how its services performed, what still needs attention and what decisions are due. Open with the few things that could change what someone does next. Put the evidence beneath that summary so readers can check the detail when they need it.

Download the editable monthly FM report workbook

Includes a blank report and a fictional example for an office building.

Start with the month, the site and the decisions

Name the site, reporting dates, services covered and who prepared the report. Say which areas or records were outside scope. For a multi-site report, identify which buildings each figure covers so a change in coverage stays visible.

Then give the reader a short summary. Include what changed since the last report, the issues that need attention and any decision with a deadline. For example, a late maintenance job matters more to the reader if they can see which area is affected and whether they need to approve access.

Show the result and where it came from

For each service measure, include the result, its agreed target where relevant, and the previous period when the two periods are comparable. Give the count behind a percentage, such as 18 of 20 jobs, and state which jobs were eligible. Link to the export, supplier report, visit record or other evidence. Include the date or period it covers.

Keep different kinds of evidence visible. A supplier update records what the provider reports. A helpdesk export records what people logged and how the team responded. A site observation describes the conditions at a particular place and time. Putting them alongside each other helps you ask a better question when they tell different parts of the story. The UK Government’s contract management guidance uses a similar principle for public contracts by pairing performance data with measures such as customer satisfaction. UK Government contract management principles

If a report is late, mark the result as awaiting evidence and give someone a date to follow up. If a definition or site boundary changed, explain the change before drawing a trend. Add a spend line where it affects a decision, with the budget, recorded spend, reporting period and any material amounts still to come through.

Keep open issues and decisions in view

Give each issue a reference and name the person or role responsible for the next step. Record the action or decision, its deadline, current status and what evidence will let you close it. Carry an unresolved issue into next month’s report with its existing reference and record any change to the deadline. Route urgent issues through your site’s escalation process when they arise.

Worked example for an office building

Fictional example. Rowan House, 1–31 October 2026. The report covers maintenance, helpdesk, cleaning and waste in shared areas on floors 1 and 2. Tenant suites sit outside the agreed scope.

Summary. Eighteen of 20 planned maintenance jobs were closed by their due date, below the agreed 95% target. The FM lead needs to approve out-of-hours access by 10 November for the two remaining jobs. The October waste return is still due from the supplier.

October service performance at Rowan House, a fictional office building
ServiceResult and comparisonSource and coverage
Planned maintenance18 of 20 on time (90%). September was 19 of 20 (95%), against a 95% target.Work-order export dated 3 November. Planned jobs due in October on floors 1 and 2.
HelpdeskFirst response within the agreed window for 27 of 29 tickets (93%). September was 28 of 30 (93%), against a 90% target.Helpdesk export dated 3 November. Eligible shared-area tickets logged in business hours.
CleaningResidue observed on the agreed floor 2 tea-point counter edge. No comparable September observation is available.Independent site note dated 21 October at 10:20. The observation covers the counter edge at the visit time.
WasteAwaiting the October return.Supplier collection return pending as of 5 November. October performance is unknown.

The maintenance coordinator will use the FM lead’s access decision to arrange the two jobs and attach completion records to the work orders. The cleaning supervisor will compare the task and use records around the visit and arrange a follow-up observation. The building coordinator will request the missing waste return by 9 November and check the dates and areas before entering the result.

Where cleaning evidence fits

Hygiene Intelligence gathers independent evidence from agreed surfaces during monthly site visits and provides a private brief for the facilities team. Use those observations in the cleaning section alongside your provider’s records. The evidence describes the agreed surfaces at the time of the visit. Your FM team owns the wider report and its decisions. Independent evidence for monthly cleaning reviews

For questions to take into a meeting focused on cleaning, get the monthly cleaning review pack by email.